Some opinions of Hunan Provincial Department of Transportation on further standardizing the management of expressway and provincial highway construction projects in our province

 

 

 

 

 

 

Xiang jiao Ji Jian [2018] No.116

 

 

Hunan Provincial Department of Transportation

Some opinions on further standardizing the management of expressway and provincial highway engineering construction projects in our province

In order to further strengthen the management of highway construction projects in our province, clarify the responsibilities of all parties, standardize working procedures, and promote the healthy and orderly development of highway construction, combined with the actual reform of highway construction management system in our province, according to the relevant laws, regulations and provisions of the state, Ministry and province, the following opinions are put forward.

One,Highway engineering construction implements the system of industry supervision and graded responsibility.

(a) the Provincial Department of Transportation is responsible for the industry supervision of highway engineering construction in the province. Specifically responsible for the supervision and management of expressway construction projects approved or approved by the national and provincial development and reform commission.

(two) the provincial highway management agencies entrusted by the Provincial Department of Transportation, responsible for the province’s highway engineering construction industry management.

(III) The Municipal Transportation Bureau is specifically responsible for the supervision and management of the common national and provincial highway construction projects included in the provincial transportation development plan within its administrative area. Other ordinary highway construction projects included in the provincial transportation development plan can be implemented with reference to this opinion.

Two, strictly implement the basic construction procedures, and effectively prevent management risks.

(4) Highway engineering construction projects must strictly implement the legal person responsibility system, the bidding system, the project supervision system and the contract management system, strictly implement the capital construction procedures stipulated by the state, and shall not violate or simplify the capital construction procedures without authorization. Transportation administrative departments at all levels should strictly examine and implement according to the management authority, and establish a sound management system and files.

(5) The provincial department of transportation is responsible for the examination and approval of construction drawings of expressway construction projects, and the relevant municipal and state transportation bureaus are responsible for the examination and approval of construction drawings of ordinary national and provincial highways.

Expressway construction projects shall be reported to the ministries and agencies by the project legal person after the organization completes the construction drawing design documents. The ministries and agencies entrusted the provincial highway management agencies to organize a review and consultation unit on behalf of the office for review., prepare the review report and put forward the industry review opinions (if the design and construction general contracting mode is adopted, the preliminary design unit shall also submit the design consultation and supervision report). For projects with complex technology, the ministries and agencies can entrust independent consulting agencies to check the construction drawing review, key parts and important structures, and the ministries and agencies will examine and approve the construction drawing budget according to the review report, verification opinions (if any), industry review opinions and the review opinions of the department’s cost management agency (except for the design and construction general contracting mode), and gradually establish and improve the construction drawing review and evaluation mechanism.

General national and provincial highway construction projects shall be reported to the relevant municipal and state transportation bureaus after the construction drawing and design documents are completed by the project legal person organization, and shall be reviewed by the municipal and state transportation bureaus and approved. The specific implementation rules shall be formulated separately by the municipalities. After the approval of the construction drawing is completed by the Municipal Transportation BureauWithin 15 working days, the construction drawing approval document shall be submitted to the provincial highway management organization for the record.

(six) highway engineering construction projects should establish and improve the quality and safety assurance system. Before the project starts, the construction unit shall go through the quality supervision procedures with the traffic quality and safety supervision institution as required. Expressway construction projects shall be submitted by the project legal person to the provincial traffic quality and safety supervision institutions, and ordinary national and provincial highway construction projects shall be submitted by the project legal person to the municipal and state traffic quality and safety supervision institutions. Traffic quality and safety supervision institutions at all levels shall promptly urge the construction unit to go through the quality supervision procedures in accordance with the regulations, and carry out quality supervision and management in a timely manner according to law.

(seven) highway construction projects shall implement the construction permit system according to law, and the project legal person shall strictly follow the "Measures for the Administration of Highway Construction Market" (ministerial order)No.11, 2015) stipulates that the construction permit procedures shall be handled, and the construction of the project without permission shall not be started. In case of violation, administrative punishment shall be imposed according to law.

For expressway construction projects, the project legal person shall apply to the Provincial Department of Transportation for construction permit, and for ordinary national and provincial highway construction projects, the project legal person shall apply to the relevant municipal and state transportation bureaus for construction permit. The transportation administrative departments at all levels shall make a decision on the construction permit according to the procedure, in which the ordinary national and provincial highway construction projects shall, after making the construction permit,Within 15 working days, the municipal and state transportation bureaus shall report to the provincial highway management agencies for the record.

(eight) highway engineering construction projects should be organized in stages according to the Ministry of Transport’s "Measures for Acceptance of Highway Engineering Completion (Delivery)" and related implementation rules.

The project legal person is responsible for the completion acceptance. After the completion of acceptance, the project legal person shall complete the project completion acceptance report in time as required, and report to the transportation administrative department that approved the project construction drawing design for the record. The completion acceptance of ordinary national and provincial highways shall be summarized by the municipal and state transportation bureaus at the end of each quarter and submitted to the provincial highway management agencies for the record. No traffic trial operation may be opened for projects that have not been completed or failed to pass the completion acceptance.  

After the project meets the completion acceptance conditions, the project legal person shall apply to the administrative department of transportation for completion acceptance. The completion and acceptance of expressways is organized by the Provincial Department of Transportation, and the completion and acceptance of ordinary national and provincial highways is organized by the local municipal and state transportation bureaus. After the completion and acceptance of ordinary national and provincial highways, the municipal and state transportation bureaus shallWithin 15 working days, the completion acceptance appraisal book will be submitted to the provincial highway management organization for the record.

Construction mileage is less than5 kilometers or a total investment of less than 50 million yuan of ordinary national and provincial highway construction projects (except bridges, long tunnels and above), can be completed and accepted by the municipal transportation bureau.

Three, strengthen the supervision of bidding process, and create a unified, open, competitive and orderly market environment.

(9) The project legal person shall follow the principles of openness, fairness, impartiality, honesty and credibility, implement the relevant laws, regulations and provisions of the state, the Ministry and the province, organize the bidding work of the project according to the approved bidding scope, bidding method and organizational form, and shall not evade bidding, discriminate against potential bidders and bidders, or implement local protection and black-box operation.

(ten) strictly implement the bidding filing management system. Expressway construction projects shall be submitted by the project legal person to the Provincial Department of Transportation for the record in a timely manner, including the qualification documents and results (if any), as well as the bidding documents and the written report on bidding (including the bid evaluation report). Ordinary national and provincial highway construction projects shall be reported by the project legal person to the relevant municipal and state transportation bureaus for the record in a timely manner, including the qualification documents and results (if any), as well as the bidding documents and written reports on bidding (including bid evaluation reports). If there are other provisions governing counties directly under the province, those provisions shall prevail.

(11) Highway construction projects shall fully implement the trading system of entering the public resource trading market, expressway construction projects shall enter the provincial public resource trading center for trading, and ordinary national and provincial highway construction projects shall enter the municipal and above public resource trading centers for trading.

(twelve) the construction projects of expressways and ordinary national and provincial highways should gradually realize electronic bidding. If electronic bidding is adopted, it shall be implemented in accordance with this opinion and the relevant provisions on electronic bidding.

(thirteen) the administrative departments of transportation at all levels shall supervise the bidding process according to the management authority, and deal with the complaints and reports in the bidding in a timely manner, and seriously deal with the illegal acts of bidding according to the law and regulations.

Four, standardize the management of engineering change, the implementation of hierarchical responsibility, prohibit unauthorized changes.

(fourteen) after the approval of the construction drawing design documents of highway engineering construction projects, they shall not be modified or changed without authorization. If it is really necessary to change the approved construction drawing design documents, it shall be implemented only after approval in accordance with the examination and approval authority. The Provincial Department of Transportation will strengthen the supervision and inspection of lowering construction standards and reducing construction scale changes.

(fifteen) highway engineering design changes are divided into two categories: highway construction projects and ordinary national and provincial highway construction projects.

1 need to improve technical standards or increase the scale of construction, and the increased investment exceeds the corresponding budget by 10% or more, and the design changes shall be reported to the original budget approval department for approval.

2. The Ministry of Transport approved the preliminary design of the expressway project, and its major design changes were reported to the Ministry of Transport for approval after the preliminary examination by the Provincial Department of Transportation.

The preliminary design of the expressway project approved by the Ministry of Transport has major design changes under one of the following circumstances; Or the provincial department of transportation approved the preliminary design of the expressway project, there is one of the following major or major design changes, submitted to the provincial department of transportation for approval:

① The starting and ending points of the route have changed;

(2) the route plan for more than 2 kilometers is adjusted continuously;

(3) the number of bridges or the structural forms of bridges and above have changed;

(4) the number of tunnels or ventilation scheme changes;

⑤ The number, location or scheme of interchange has changed;

6. The charging method, site location and scale have changed;

⑦ The standard and scale of the connecting line have changed;

(8) The type, width and thickness of pavement structure change;

Pet-name ruby management, maintenance and service facilities change in location, quantity and scale.

The remaining major design changes are entrusted to the project legal person for self-examination and approval. After the approval is completed,Report to the Provincial Department of Transportation for the record within 15 working days. General design changes shall be reviewed and approved by the project legal person.

3. The design changes of ordinary national and provincial highway construction projects (including technically complex projects) shall be formulated by the municipal transportation bureaus themselves, and the construction scale and technical standards shall not be arbitrarily reduced. It is a major design change, such as the change of the starting and ending points of the route, the adjustment of the route scheme for more than 1 km in a row, the change of the width of subgrade and pavement, the change of the overall pavement structure type, the change of the structure type and scale of the extra-large bridge, and the increase or decrease of the number of bridges and tunnels above the bridge. Within 15 working days after the completion of the approval, the municipal transportation bureau shall report to the provincial highway management organization for the record.

(16) Transportation administrative departments at all levels should strengthen the supervision and management of engineering design changes, and seriously investigate and deal with unauthorized changes, illegal changes, dismembered changes to avoid approval and other irregularities.

(seventeen) the project legal person should strengthen the project cost management and strictly control the project investment. In the process of project implementation, the budget estimate should be strictly taken as the highest control amount of project investment. If it is really necessary to exceed the budgetary estimate, the budgetary estimate shall be examined and approved in strict accordance with the relevant provisions. Transportation administrative departments at all levels shall strengthen the supervision and inspection of highway engineering cost activities in accordance with their duties and powers.

Five, strict market access, strengthen contract management, strengthen industry supervision, to ensure the quality and safety of the project.

(eighteen) highway and ordinary national and provincial highway construction projects shall implement the project legal person responsibility system according to law. The project legal person can manage the project by itself, or entrust a qualified management unit to manage it.

The technical and management capabilities of the legal person of the expressway construction project or the organization and personnel of the management unit entrusted by it shall conform to the Opinions of the Ministry of Transport on Further Strengthening the Management of the Highway Project Construction Unit.No.438 [2011]).

The legal person of provincial highway construction project or its entrusted management unit, organization and personnel shall meet the following basic conditions:

1. The organization has major functional management departments such as planning, contract, engineering, finance, quality and safety, with clear division of responsibilities and perfect management system;

2. The person in charge of the project is familiar with the national laws and regulations on engineering construction, with good political quality, high professional level, good reputation in the industry, more than 3 years of engineering management experience, and has served as the person in charge of one or more highway projects or the deputy person in charge of two or more projects, and should have intermediate or above titles;

3. The technical person in charge of the first-class highway and the construction project containing tunnels and extra-large bridges has the title of senior or above in highway engineering, has rich engineering experience, and has served as the technical person in charge of two or more highway engineering projects; The technical person in charge of highway construction projects of Grade II and below has the title of intermediate or above in highway engineering, has rich engineering experience, and has served as the technical person in charge of one or more highway projects or the technical personnel of two or more projects;

4. The first-class highway construction projects should have more than 5 engineers and technicians with intermediate titles or above in highway engineering, and the second-class highway construction projects should have more than 3 engineers and technicians with intermediate titles or above in highway engineering. Financial personnel should have the ability of financial accounting.         

When the preliminary design documents of the project are submitted for approval (including the first-stage construction drawing design documents), the highway project construction unit shall report the management institutions, management personnel and qualifications stationed at the project site to the relevant transportation administrative departments for verification. The competent department of transportation shall timely review, and those who fail to meet the qualification standards shall be instructed to supplement and improve, or instructed to entrust a construction agent with corresponding management capabilities to be responsible for construction management. In the process of project construction, the change of main personnel such as the project leader or technical leader shall be reported to the relevant transportation administrative department for verification.

(19) highway design, construction, supervision, testing, consulting and other business units shall have corresponding qualifications, fully perform their obligations in accordance with the provisions of the contract, and prohibit acts such as relying on lending qualifications, subcontracting and illegal subcontracting.

(twenty) the project legal person should strengthen the management of contract performance, include the breach of contract and the liability clauses in the bidding documents or contract documents, and establish and improve the penalty and assessment incentive mechanism for breach of contract.

(21) The project legal person shall formulate and improve the management system of project quality, safety, progress and cost, effectively improve the management ability and quality, establish and improve the project quality and safety assurance system, implement the project quality responsibility registration system and lifelong responsibility system, vigorously promote the standardization construction, further strengthen the project quality and safety management, and ensure the inherent quality and durability of the project, and ensure the quality and safety of the project.

(twenty-two) transportation administrative departments at all levels should strengthen information management, and gradually establish an information management platform for highway construction. Make full use of information means such as big data and cloud platform, implement dynamic management of information such as performance of highway construction project personnel, and effectively improve the supervision ability and level of the industry.

(23) Provincial highway management agencies should earnestly fulfill the management responsibilities of highway engineering construction industry in the province, and focus on strengthening the guidance and supervision of the approval of construction drawings, construction permits, construction management, design changes, and completion (handover) acceptance of provincial highway construction projects.

(24) transportation administrative departments at all levels and industry management institutions should strengthen industry supervision, and organize comprehensive supervision and special supervision of highway construction markets and construction projects within their jurisdiction according to management authority, and all inspection results should be included in market credit records, annual transportation target assessment and quality work assessment. The illegal acts found by the inspection shall be punished according to the management authority.

(25) The Municipal Transportation Bureau is responsible for the supervision and management of national and provincial highway construction, adoption and transfer of ordinary highways, and shall, in accordance with the construction, management and transfer plan approved by the local people’s government and relevant regulations, promptly clarify or adjust the custody responsibilities of relevant units during the project construction period and the adoption institutions after the completion, and strengthen the supervision and management of project adoption and transfer.

VI. Others

(26) departments at all levels should earnestly strengthen the building of a clean government, improve the working mechanism, strengthen the management of projects and personnel, plug management loopholes from the system and mechanism, establish and improve a long-term mechanism for preventing and punishing corruption, build sunshine transportation, and enhance the image of the industry.

(27)This opinion is fromIt will come into force on August 1, 2018 and will be valid for 5 years.

 

 

 

Hunan Provincial Department of Transportation    

July 12, 2018

Hunan Provincial Department of Communications Office                Printed on July 27th, 2018

Recruits please join the ranks: a real and vivid "growth diary" of recruits

How does a recruit grow into a qualified soldier in 180 days and nights? "Recruits please join the ranks" goes deep into the record and observation of the recruit training base, and is serious and lively, showing the process of quenching the recruits into steel after 00.

Author: Zheng Changhua

How many steps does it take from ordinary people to soldiers? Establish rules, organize internal affairs, conduct actual combat training, and conduct rigorous assessment … Recently, the military documentary "Recruits Please Join the ranks" jointly produced by Tencent Video and CCTV was broadcast online, and the whole process of the recruits growing into qualified soldiers was recorded by lens.

 

The program consists of seven periods, each with a theme. Starting with "Why did I choose to be a soldier", it has gone through 180 days and nights, spanning 20,000 kilometers, and went deep into the recruit training base of the three armed forces, telling the stories of recruits and military camps with short stories and true details.

Youth stories of recruits after 00

The recruits come from all over the world, with different life experiences and different temperaments, but they all come to the same place-the military camp with their love for the motherland.

 

Xu Menghao, high flyers, Department of Philosophy, Peking University, likes reading and Henan Opera; Duan Runzhi, an undergraduate student, is lively and excellent in learning, and is what people call "the child of others"; Lin Junlong, born by the sea, used to be a chef in a five-star hotel; Cai Zhuoyu, a fine arts major, hopes to paint in the blue sky with fighter planes after entering the military camp … Such a group of young people constitute the epitome of the whole film’s recruit camp.

 

"Recruits please join the ranks" aims the camera at these recruits after 00 and records the process of their tempering into steel. This tempering process is naturally full of hardships and challenges.

 

"It’s too difficult to turn a quilt into a tofu block!" Duan Runzhi, an army female soldier, never thought that she would "cushion the bottom" in a late-night emergency pull. The instructor’s minimum requirements became her "ceiling". The first packing was completely out of specification, and the second packing was successful, but she was criticized by the instructor for being too slow.

 

The air force brigade will fuck, and Class 9 will win the championship in one fell swoop. The joy of "counterattack" didn’t last long, and the pull-up project suddenly turned Cai Zhuoyu and Lin Junlong back to the prototype of "rookie". Physical fitness test, their scores hit a new record low, waiting for them is the "devil" training customized by the squad leader for them.

 

"It’s very real" and "It’s so good to cry" … Since the broadcast of "Recruits Please Join the Team", it has gained a lot of attention among young audiences. The protagonists of these stories do not have their own aura, but ordinary young people. Putting them in a special living environment, their stories naturally collide with the audience.

 

The film focuses on interacting with young netizens and strengthening dialogue with the audience in a full-fledged presentation. On the one hand, it is a humorous panoramic record of the recruits’ state. The rotation is left and right, the singing of military songs is out of tune, and the squad leader directs his comrades to "hit the tree" … A series of "god operations" with their own jokes make the work more grounded; On the one hand, Wang Bingbing, a reporter from the General Station, is the narrator, and the relaxed and humorous comment language such as "Mother learns to bully", "paddling to fish", "being rubbed by reality" and "Voldemort" not only adds a sense of delicacy to the film, but also adds youthful expression.

The growth story from youth to soldiers

Director Zhao Yunze said: "Before officially contacting this project, it is hard to imagine how the army trained ordinary people into soldiers in batches in just six months."

 

The director’s curiosity is also the breakthrough of the film.

 

Before joining the army, the recruits’ imagination of the military camp was intense and grand; After joining the army, their reality in the new barracks is to stand at attention at ease and have a little routine. "Recruits Please Join the Rank" concentrates the six-month time that these recruits entered the military camp after 00 in chronological order, and records their growth stories in the "conflict" and dynamics.

 

The title of "Peking University" did not give Xu Menghao more superiority. He was appointed as the monitor of the new recruits, and one of his duties was to upload and issue. It seems simple, but it is challenging: this requires him to have both excellent basic skills and high emotional intelligence, otherwise it will be difficult to convince the public.

 

In the updated program, Xu Menghao hit a wall when he first exercised his monitor’s rights. "Everyone is a recruit. Why do you command everyone to work?" Some comrades-in-arms disagreed with the way he assigned work and complained. With the help of veterans, Xu Menghao gradually realized that there was a big problem in his way of doing things. In the latest "picnic", he took the initiative to integrate into group activities and finally realized the "breaking the ice" with his comrades.

 

The program focuses on the intuitive response of recruits to setbacks, and outlines a "deformation meter" belonging to recruits in the low valley-contradiction-growth. Under the lens of the program, every recruit’s body and soul are being "scattered" and "reshaped" again. In the process of recording, in addition to the principle of non-intervention, the program also used another method-giving the microphone to the recruits.

 

At the end of the first program, the recruits can finally contact their families. Some people burst into tears at the sound of their family members, some people cried because they missed their mother and asked her to take more photos and send them to them, and some people told their families to have a good meal … A homesick greeting instantly "returned" the recruits to their prototype. At this moment, homesickness spread among them, without concealment or restraint, and all feelings broke through the screen. Iron soldiers are accompanied by deep affection, and the program outlines the true appearance of teenagers in real records.

 

As a co-producer, Tencent Video continues to connect with the audience in a young voice and novel expression. From How to Talk about this painting to The Great Qin of the Fresh Museum, and this time, the new recruits are invited to join the ranks. The themes are different, but they are all constantly "new" in expression. This time, "Recruits please join the ranks" aims at the recruits, which is a new exploration of the young expression of military themes. In the follow-up program, what are the unknown training programs for the sailors of the "One Speciality and Many Capabilities" warship, how to train the female soldiers of the "Snow Lotus on the Plateau" garrison in Tibet, and how the airmen of the "Blue Angel" air force guard Hawk to complete the battle will all be shown one by one.

Editor | Sui Fangfang Ning Yahong

The film "defiant" exposed the role poster, and the little people overturned the big power.


1905 movie network news Written and directed by Yang Bingjia, Wei Junzi as producer, Zhang Zhe as producer, Pengfei Qin as action director, starring Gao Weiman, Xiang Hao, Liu Ben and Zhang Di, will be launched on June 3rd. A few days ago, the film released the role poster, and all the characters with clear distinction between right and wrong appeared. The situation that the little people fought against the big forces was quite refreshing, and the new amazing role of Xie Miao, the most popular man in the Internet University, was even more exciting.


In the role poster exposed in the film "Arrogant", powerful and insidious big men and heroic and unyielding little people confront each other, and a strong sense of modern crime types overflows under the ancient costume. Cheng Blind Man (Xie Miao) was originally just a "knife catcher" who paid money to handle affairs. He met Niyan (Gao Weiman), a drunken woman who was slain and humiliated, by chance, and his brother Nijun (Zhang Haosen) was killed by Yu Wenying (Xiang Hao), a top power. Yu Wenying is extremely well-dressed and cruel, and regards human life as dirt. His minions He Qiufeng (Liu Ben) and Heijiao (Kang Xuan) are all sinister and vicious. As a blind man, he was furious and took the road of seeking justice for revenge, and Qin Niang (Zhang Di), a former confidante on the battlefield, did not hesitate to die together and was involved in this powerful dark dispute. In the poster, the role declaration highlights the confrontation between good and evil camps. The more brutal and insidious the big forces are, the more brave, unyielding and affectionate the little people are. After the poster was released, some netizens said: "It is this disparity in power that shows the dramatic tension and the soul of the characters. This film has held the cool feeling of crime movies to death."


Xie Miao, who is known as "the most popular man in the Internet University", has led the leading role in "Arrogant". No matter from the action design or the role richness, Xie Miao has ushered in a milestone in his personal film history. Cheng Blind, played by Xie Miao, originally didn’t intend to avenge Ni Yan. In the film, the protagonist witnessed and experienced the cruelty and injustice of evil forces, and finally the former god killer was awakened to start a refreshing revenge war. In addition, Xie Miao tried to close his eyes for the first time in the whole action scene in the film, and the excitement increased with the difficulty of the action. Xie Miao said: "If there’s one play that I can fully play, I think it’s" Arrogant ". Maybe I have accumulated so many plays before, just to become a blind man. " Wei Junzi, a producer of the film and a senior genre researcher, said: "This will be the beginning of a new stage for Xie Miao as an actor and an action actor." Before the release of the preview, some netizens were very much looking forward to Xie Miao’s new film and commented: "He is a good actor who should have been on fire long ago!"